Capital Improvement Projects Update April, 2016

Gardiner-Demolition

Kenston’s Capital Improvement projects are underway. The Board of Education approved the bids for Gardiner Center and the Stadium projects at the March meeting. Legacy Construction was awarded the contract for the general construction work.

Playground equipment has been removed that can be safely reused. Demolition will begin at Gardiner next week. The site is closed to the public until further notice.

The practice field between the middle school and stadium will be a construction staging area and off limits until further notice.

Beginning April 4th, school buses will be parked in the high school bus loop and vans in KIS parking lot near the bus garage in preparation for stadium construction.

Beginning May 1st, demolition of the Home bleachers and construction of the restrooms will begin. No events are to be scheduled in the stadium after May 1st.